Home
Products
Projects
Articles
For More Information
Links
Frequently Asked Questions
Authorized Distributors

Enviro-Prep System Quarterly Update Newsletter

*




Email Marketing by VerticalResponse

CASE HISTORIES

Highway 31 Bridge - Elk Rapids, MI

Enviro-Prep® was sprayed on the two bridge abutments by the MDOT maintenance crew at thicknesses near 20 wet mills. After allowing the product to dry (about 1 hour), the steel was sand blasted with expendable grit. The field crew reported a noticeable decrease in dusting during removal, as compared to normal operations. The untreated waste (paint chips plus media) was hazardous, and the treated waste was nonhazardous. The results were:

TCLP Lead (mg/l)
Untreated Waste 22.0
Waste plus 20 wet mils Enviro-Prep® 0.48

(back to top)

Water Tower - Midland, TX

Enviro-Prep® was sprayed on the tower, but this time at various thicknesses (10, 15, and 20 wet mils) to determine the optimum (minimum) thickness to achieve non-hazardous lead results. All three thicknesses resulted in non-hazardous waste, with the 20 mil application achieving non-detectable levels of lead. The product and the original coating were removed with normal sandblasting techniques, and the waste was disposed of as non-hazardous. The results were:

TCLP Lead (mg/l)
Untreated Waste 122.0
Waste plus 10 wet mils Enviro-Prep® 1.9
Waste plus 15 wet mils Enviro-Prep® 0.25
Waste plus 20 wet mils Enviro-Prep® <0.2

(back to top)

International Bridge - Sault Ste. Marie, MI

Enviro-Prep® on this project was applied with and airless spray pump. The contractor used 150" of 1/4" ID airless hose, and a RAC IV #631 spray tip. The product was applied at 20 wet mills and removed with recyclable grit. This particular portion of the job used 50 gallons of product, which equates to roughly 5,000 sq. ft. of steel. The contractor was able to apply the product in the morning and began blasting about two hours after applying it. The air temperature was in the upper 30's to low 40's, with a brisk wind passing through the Soo Locks. This project required full containment that provided for warmer application conditions. The results were:

TCLP Lead (mg/l)
Untreated Waste 120.0
Waste plus 20 wet mils Enviro-Prep® 0.53

(back to top)

Water Tower - Rocky Gap State Park, Cumberland, MD

This project required a 10 wet mil application of Enviro-Prep® to an aboveground water storage tank 40 feet high and 15 feet in diameter. The job was started on a perfectly sunny fall day, which allowed the product to dry in as little as 30 minutes, and was completed the following morning in a heavy morning fog. A Graco Bulldog Airless Sprayer was used with a #635 airless spray tip, 50' of 3/8" ID hose followed by 100' of 1/4" hose. The contractor also took out all filters in the gun and pump to increase spray efficiencies. The paint and Enviro-Prep® were removed with expendable grit. The job consumed a total of 100 gallons, with approximately 80 gallons used on the outside and top and the remainder used inside on the ceiling. The contractor saw significant savings by using Enviro-Prep® because the benefit of reduced dusting and non-hazardous waste allowed him to use a one-drop containment structure. The contractor figured his costs to be about $0.10 - $0.14 a sq. ft. and his non-hazardous waste disposal costs to be $300.00 - $400.00 less per drum than hazardous waste. The test results were as follows:

TCLP Lead (mg/l)
Untreated Waste 56.0
Waste plus 10 wet mils Enviro-Prep® <0.50

(back to top)

Chip Silo Supports - Springfield, OR

SPRINGFIELD, OR: "During our September mill maintenance shutdown we endeavored to clean and paint the structural steel supports inside one of our large chip silos. We have four such vessels and have undertaken this work on two of them previously.

"The project began early swing shift on Sunday and proceeded on or ahead of schedule until about 5:30am on Wednesday. During the pressure-washing phase of the job the painting foreman observed what appeared to be lead primer under the topcoat of steel. The paint was then tested and found to contain high levels of lead. The two silos we worked on previously are of the same vintage and construction but had no lead-based paint in them. Nor could we have tested for lead before the shutdown because the steel is inaccessible under operating conditions.

  • "The sandblasting phase of the work could not proceed because the personal protective gear and engineering controls were not in place for an OSHA-compliant lead abatement project. But the lead posed another problem. EPA classifies our mill as a "small generator" of hazardous waste. We plan our abatement projects quite carefully to avoid exceeding the monthly limits of hazardous materials necessary to maintain that classification. By the time this project got underway, we had already reached out monthly limit for waste generation... with 8 days to go before the start of a new month. Furthermore, this project would generate 4 times our monthly limit!

"We had two choices at this point:

  • Abandon the painting job and wait for a later 7 day mill outage opportunity, or
  • Acquire and use a lead "neutralizer" product, such as ENVIRO-PREP® that would permit us to proceed with blasting and painting, albeit with some schedule delay. (ENVIRO-PREP® is a non-hazardous product we have screened and tested on another project.) Our tests have demonstrated that it is effective at rendering lead paint to non-detectable in TCLP (toxicity characteristic leaching procedure) tests and therefore not regulated by the EPA. This product converts the soluble lead compounds to harmless metal salts... in this case, lead phosphate.

"We called Hoffer's Coatings, Inc. in Wausau WI at 6:15AM PST and asked them to assemble 60 gallons of ENVIRO-PREP® and prepare it for immediate shipment by air. At about 8AM our purchasing manager contacted corporate aviation to arrange a charter that could get the product to our mill immediately. By 4PM that same day the painting contractor was applying the ENVIRO-PREP® in the silo. During the day they had set up their clean rooms, changing stations, air compressors and implemented engineering controls for a full lead abatement project. They had also drafted a project lead compliance program and a fall protection program for our review and approval. Arrangements were made to collect the spent blasting media and store it in a secure area on site pending the results of TCLP tests to confirm its disposability.

"The sandblasting actually went a little faster than planned and we did some creative scheduling to recover the balance of the lost time. The project finished within 2 hours of the original plan and production was not impacted. TCLP tests performed on the 8,000 lb. of spent blasting media indicated that ENVIRO-PREP® had, indeed, rendered the lead to be non-detectable. It was then hauled to a landfill with no special documentation required or extraordinary disposal costs incurred.

"In the process of researching ENVIRO-PREP® our environmental team learned of several other products that claim to be as effective as this one. However it appears that some of these contain lime and portland cement which really do nothing to remove the hazardous lead compounds but simply act to defeat some of the testing processes used to detect them."

(back to top)

 

NOTE: We have moved our MSDS and Data Sheets to a secure location. Please call or email for access.


Legal Notice and Warranty

Copyright © 1999-2008
hci-Hoffer's Coatings, Inc. Wausau, Wisconsin
Hoffer's Coatings Inc., Wausau, Wisconsin
For more information call (800) 596-6282 Or email